Table of Contents | ||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Project Assignment
Ref | Responsible | Task | Links | |||
---|---|---|---|---|---|---|
1 | Team LeaderProject Manager | Create a Confluence page for the Project (“Project Confluence”) | ||||
2 | Team LeaderProject Manager | Create a Folder inside the MS Teams Resources page so that the project team will have common storage of files | 3 | Team Leader | Assign the project to the PM and consultant via meeting, where TL will discuss the contract. | 4https://staria.sharepoint.com/:f:/g/netsuite/EvIUqfSh_otJo8rQCtuxekIBitmSfHb6Nkvj6EaUIa1Chw?e=9JoDVj |
3 | Project Manager | Coordinate all the SOW and BRD to the NetSuite team if there is a NetSuite implementation. If it’s standalone implementation, then PM will review the SOW
| ||||
4 | Consultant | Review the SOW 6 | ||||
5 | Project Manager | Request Star IT team to create Staria Admin (SA) and Staria Integration (SI) email. The format for
| ||||
6 | Project Manager | Create Invoicing page on Project Confluence |
...
Kick off
...
Responsible | Task | Links | |
---|---|---|---|
1 | Project Manager | Conduct Kick Off
|
...
Pre-configuration
Responsible | Task | Links | |
---|---|---|---|
1 | Consultant | Once access is available, email request to Team Leader for bundle provisioning to the Client's Account ID | |
2 | Consultant | Update NetSuite employee record email to the Staria Admin and create Keeper credentials | |
3 | Ben or Product(Jhelver) | Consultant will request to Jhelver/Ben to Provision Poland bundle to Client’s Account ID | |
4 | Consultant | Install and Setup the Poland Localization | |
5 | Consultant | Conduct Unit Testing |
...
Integration email MUST be available and integration is working already.
Client needs to send at least 3 test invoices per subsidiary, that will be used in testing.
Ref | Responsible | Task | Links | |||
---|---|---|---|---|---|---|
1 | Project Manager | Schedule a bi weekly/weekly project meeting with the client | ||||
2 | Consultant | Create UAT Template |
| |||
3 | Consultant | Schedule 2 UAT meetings
| ||||
4 | Project Manager/ Consultant | Obtain UAT Sign off from client. Refer to the link for the template. | ||||
5 | Project Manager | Save UAT Sign off in Teams folder and Update Project Confluence page to attach the link to the sign off document | ||||
6 | Project Manager | Request Integration Setup for Production Deployment. This request should be done at least 1-2 weeks prior go live. 7 | Project Manager/ Consultant | Request access to client’s production account |
...
The standard timeline for this is 1 week. This is to include the integration setup.
...
Responsible | Task | Links | |
---|---|---|---|
1 | Consultant | Create Go Live Checklist page in Confluence/wiki/spaces/SPR/pages/1231683684 | |
2 | Consultant | Using the Go Live Checklist, Deploy all Poland setup to Production | |
3 | Project Manager | Follow up/confirm if the integration is already setup into production by the partners | |
4 | Consultant | Notify Project Manager and Client when setup is done | |
5 | Project Manager | Send a Go Live Email to Client and SuiteApp Project team |
|
...
Hypercare
...
Responsible | Task | Links | |||||
---|---|---|---|---|---|---|---|
1 | Consultant | Schedule 2 Hypercare Meetings:
| 2 | Project Manager |
| ||
2 | Consultant |
| |||||
3 | Project Manager | Conduct a meeting for the Support process and send an email guide for the Support process |
| ||||
4 | Consultant | Update Functional Document Template Confluence page |
...
Project Closing
Responsible | Task | Links | |
---|---|---|---|
1 | Project Manager | Schedule a meeting for the project closing |
|
...